WCMES Expects To Restore Power Tuesday

Weakley County Municipal Electric is continuing to get customers back on line following the storms that rolled across the Ken Tenn area Sunday. WCMES Engineer Hunter Wood says the WCMES hopes are to have all that can be back on line, should be on line Tuesday.

Wood said there will be additional customers who will have to contact an electrician to help restore power back to their home or business before electricity can be restored.

Wood said Fulton Electric assisted WCMES in getting a substation re-energized while WCMES was working to restore power.

Approximately forty crewmen have worked essentially worked almost non-stop to restore electricity.